January 2021
Happy New Year!

Works to the exisiting structure of the Hills Apartments is nearing completion and new internal structural steel in being installed with the balcony steel to follow. Following this, the roof is to be installed which will be a major milestone for this project.

All piling work to the carpark is complete with foundations now being built and the first concrete pour due in late January.

Works are also about to begin on the construction of a new slope stability wall. This runs around the southwest corner of the Hills Apartments and is a difficult task that involves more piling. Excavation will begin this month to get this particular area ready for the piling machine. Piling is scheduled to begin at the end of February.

You will notice a bit more activity through the Bridge Street entrance as trucks are needed to remove material from the areas we are working on. Contractors have been asked to be extra vigilant when using this driveway and to meet the requirements of the traffic management plan.

210122 West view of site 2.jpg
210122+South+East+view+of+site.jpg
Screen Shot 2020-12-22 at 8.57.56 AM.png

December 2020
We have a new roof structure!

Christmas is on the horizon and there is a lot happening on site before the Christmas break.

If you've passed the site in the last few weeks, you will have seen the roof structure has been lifted into place. This now shows to the full scale of the building.

On site, construction of insitu walls on level one is nearing completion. Following this, construction will then move up to level two. New structural steel is being installed on level three and the ground floor. Minor demolition works continue, including cutting openings for new staircases and windows.

The new garages are also under construction and excavation is complete with foundations about to commence.

In the car park, a new sewer line and manhole have been installed with excavation nearing competition. If you take a look on site, you'll see the piling rig is now onsite with piles set to be installed in later this month. The Council has also installed the site's new stormwater connection on Clyde Street.

There are just a few Courtyard Apartments available. For more information, contact one of our Lodge agents

North east view of carpark.JPG
South view of Hills Residence.JPG

November 2020
A new roof to be installed.

Hills Apartments - Structural work to the Hills Apartments building foundations and new insitu walls on the ground floor are now complete. Insitu walls on level 1 will be poured next. 

Sections of the roof structure are being built on the ground and you will see these lifted into place later in November.

Hills Village Car Park - The concrete wall around the perimeter and over half of the excavation work is now complete with new sewer and stormwater services being laid. 

There are just a few Courtyard Apartments available. For more information, contact one of our Lodge agents

IMG_4565.JPG
IMG_4580.JPG
Screen Shot 2020-12-22 at 8.57.56 AM.png

October 2020
A hive of activity at Hills Village.

The Hills Apartments are taking shape. Structural work to exisiting foundations and walls is ongoing with the majority of new footings complete. Structural steel to form new staircases is being installed and structural steel for the roof has been fabricated off-site, ready for installation later this month.

Work on the carpark continues with gardens and demolition on the Clyde Street side now complete. Piling work to form the temporary retaining wall is ongoing and excavation will recommence shortly. The old sewer line will also be replaced later this month.

Site establishment is near completion with facilities for workers now installed and the hoarding along Grey Street will have a full graphic installed later this week.

The showroom container has been relocated to the river end of the site with a great view over the site. Appointments are now by appointment only and can be arranged through our Lodge agents

IMG_3735.JPG
200903 Drone view North east.JPG
 

September 2020
Hills Village is taking shape.

Stage one of excavation of the ANZAC site is near completion. Site offices and welfare facilities will now be set up for the onsite project team. 

At the end of August, the Stark Property team and project contractors gathered with local iwi representatives for a site blessing.

Demolition to gardens and walls on Clyde Street has just begun and foundation improvements to the Hills building is ongoing.

Over the next couple of weeks, the site will continue to be cleared and the retaining wall construction will commence, beginning with drilled concrete piles and followed by excavation towards the Grey Street end of the site.

The showroom container will also be relocated to a new position to allow for work to continue.

200903 Drone view west.JPG
Hills Blessing-6341.jpg
IMG_3555.JPG
 

August 2020
Work continues steadily at the Hills Apartments.

To facilitate the build of the underground carpark, excavation work and piling of the temporary retaining walls will commence before the end of the month.

The showroom container will also be relocated.  

Work on the Hills Apartments continues steadily seeing the foundation work almost fully completed. We are expected to see the completion of the ground floor drain laying this month and structural steel will begin to arrive on site, while new openings for windows and doors are created. 

IMG_3340.JPG
IMG_3337.JPG
Screen Shot 2021-01-22 at 3.34.56 PM.png
 

July 2020
Construction updates – 70% of the value of Stage One now sold.

After a big few months of work, major demolition to the old Hills Laboratories building is now complete.

Driving past the 1 Clyde Street site, you can see the carcass of the existing building cleared and ready for contractors, SJR Builders, to commence the apartment build and fit out. Construction will begin later this month, alongside some initial concrete, structural steel and early services work.  

Early in August, the old petrol station located on the front, Grey Street side of the site will be demolished followed by excavation work for the new basement carpark that will service the apartments.

IMG_2016-2.jpg
IMG_3030.JPG
 

June 2020
Construction updates – on track for completion mid-late 2021.

The floor has been ground and demolition work is nearing an end making way for the commencement of construction.

The car park and the commercial building continue to make progress and move forward positively.

IMG_3108_e.jpg
Background9.jpg

March 2020
Demolition continues to progress on the former Hills Laboratories building.

Demolition is nearing completion and gridlines are being set out on the Hills Apartments. The commercial building design continues to be developed while the car park portion of the project has gone out for tender.

IMG_20200205_094703.jpg
IMG_20200205_094717.jpg
Screen Shot 2020-06-11 at 11.57.47 AM.png

January 2020
Demolition and design underway at the Hamilton East site.

The architectural refurbishment of the former Hills Laboratories building currently underway with the demolition team on site, stripping the building back to the bare basics and removing the rooftop.

The commercial precinct and underground car park are both in design phase.

IMG_20200123_100249 (Custom).jpg
IMG_20200123_100558 (Custom).jpg